風管系統(tǒng)的安裝宜在施工區(qū)域建筑圍護結(jié)構(gòu)施工完畢、安裝部位和操作場所清理后進行。凈化風管系統(tǒng)應在安裝部位的地面已完成、墻體面層工序施工完畢、室內(nèi)無飛塵或有防塵措施且能夠滿足初級凈化后進行安裝,安裝過程中產(chǎn)生的雜塵應及時清理并確保符合初級凈化的要求,中斷安裝時應對管口進行封閉。
The installation of the air duct system should be carried out after the completion of the construction of the building enclosure structure in the construction area, and after the cleaning of the installation site and operating area. The purification duct system should be installed after the installation site has been completed on the ground, the wall surface construction process has been completed, there is no flying dust or dust prevention measures indoors, and it can meet the requirements of primary purification. The miscellaneous dust generated during the installation process should be cleaned up in a timely manner and ensured to meet the requirements of primary purification. When installing, the pipe mouth should be closed.
風管安裝前應完成風管位置、標高、走向的測量、定位:放線及技術復核,且符合設計要求。建筑結(jié)構(gòu)的預留孔洞位置應正確,孔洞應大于風管外邊尺寸100mm或以上。
Before installing the air duct, the measurement and positioning of the position, elevation, and direction of the air duct should be completed, including laying out and technical review, and meet the design requirements. The reserved hole position of the building structure should be correct, and the hole should be 100mm or more larger than the outer size of the air duct.
搬運風管應防止碰、撬、摔造成其機械損傷,安裝時不應攀登倚靠風管。
When transporting air ducts, precautions should be taken to prevent mechanical damage caused by collision, prying, or falling. During installation, do not climb or lean against the air ducts.
風管安裝前應對其外觀進行質(zhì)量檢查,并清除其內(nèi)外表面粉塵及管內(nèi)雜物。安裝中途停頓時,應將風管端口封閉。
Before installing the air duct, its appearance should be inspected for quality, and dust on its inner and outer surfaces as well as debris inside the duct should be removed. When there is a pause during installation, the air duct port should be closed.
風管接口不得安裝在墻內(nèi)或樓板內(nèi),風管沿墻體或樓板安裝時,距墻面不宜小于200mm:距樓板宜大于150mm。
The air duct interface shall not be installed inside the wall or floor. When the air duct is installed along the wall or floor, the distance from the wall should not be less than 200mm, and the distance from the floor should be greater than 150mm.
安裝在易燃、易爆環(huán)境或輸送含有易燃、易爆氣體的風管系統(tǒng)應設置可靠的防靜電接地裝置;輸送含有易燃、易爆氣體的風管系統(tǒng)應在通過生活區(qū)或其他輔助生產(chǎn)房間外部設置接口。
Reliable anti-static grounding devices should be installed for air duct systems installed in flammable and explosive environments or transporting flammable and explosive gases; The air duct system transporting flammable and explosive gases should have interfaces installed outside the living area or other auxiliary production rooms.
風管穿過封閉的防火、防爆的墻體或樓板時,應設置鋼制防護套管,防護套管厚度不小于1.6mm,風管與防護套管之間應采用不燃柔性材料封堵嚴密。穿墻套管與墻體兩面平齊、穿樓板套管底端與樓板底面平齊,頂端應高出樓板面30mm。
When air ducts pass through enclosed fire-resistant and explosion-proof walls or floors, steel protective sleeves should be installed with a thickness of not less than 1.6mm. Non combustible flexible materials should be used to seal tightly between the air ducts and the protective sleeves. The wall sleeve should be flush with both sides of the wall, and the bottom end of the floor sleeve should be flush with the bottom surface of the floor. The top end should be 30mm higher than the floor surface.
風管安裝還符合下列規(guī)定:
The installation of air ducts also complies with the following regulations:
風管內(nèi)不應有其他管線穿越。
There should be no other pipelines crossing through the air duct.
不應利用避雷針或避雷網(wǎng)作為室外風管系統(tǒng)拉索的金屬固定件。
Lightning rods or lightning nets should not be used as metal fasteners for outdoor duct system cables.
輸送空氣溫度高于80℃的風管應按設計規(guī)定采取安全可靠的防護措施。
Ducts that transport air with a temperature higher than 80 ℃ should be equipped with safe and reliable protective measures according to design specifications.
風管與建筑結(jié)構(gòu)風道的連接接口,應順氣流方向插入,并應采取密封措施。
The connection interface between the air duct and the building structure air duct should be inserted in the direction of airflow and sealed.
輸送產(chǎn)生凝結(jié)水或含蒸氣的潮濕空氣風管,安裝坡度應按設計要求,并應在管底最低處設置帶封堵的泄水管口。風管底部不宜設置拼接縫,拼接縫處應做密封處理。
The installation slope of damp air ducts that produce condensed water or steam during transportation should be in accordance with design requirements, and a sealed drain pipe should be installed at the lowest point of the pipe bottom. The bottom of the air duct should not have joint seams, and the joint seams should be sealed.
風管(不包括獨立的排煙系統(tǒng))與風機、風機箱、空氣處理機等設備相連處,應設置柔性短管,其長度為150mm~300mm或按設計規(guī)定。柔性短管不應作為找正、找平的異徑連接管。管穿越結(jié)構(gòu)變形縫墻體的兩側(cè),應設置滿足系統(tǒng)功能長度為150mm~300mm的柔性短管,距離墻體宜為150mm~200mm。
Flexible short pipes with a length of 150mm~300mm or as specified in the design should be installed at the connection between air ducts (excluding independent smoke exhaust systems) and equipment such as fans, fan cases, and air handling units. Flexible short pipes should not be used as reducing connecting pipes for alignment and leveling. Flexible short pipes with a functional length of 150mm~300mm should be installed on both sides of the deformation joint wall of the pipe passing through the structure, and the distance from the wall should be 150mm~200mm.
風管測定孔應設置在不產(chǎn)生渦流區(qū)的便于測量和觀察的部位;吊頂內(nèi)的風管測定孔部位,應留出活動吊頂板或檢查門。
The air duct measuring hole should be set in a location that does not generate eddy currents and is convenient for measurement and observation; The location of the air duct measurement hole in the ceiling should leave a movable ceiling panel or inspection door.
風管安裝偏差應符合下列規(guī)定:
The installation deviation of air ducts shall comply with the following regulations:
明裝水平風管水平度偏差不得大于3mm/m,總偏差不得大于 20mm。
The horizontal deviation of the exposed horizontal air duct shall not exceed 3mm/m, and the total deviation shall not exceed 20mm.
明裝垂直風管垂直度偏差不得大于2mm/m,總偏差不得大于 20mm。
The vertical deviation of the exposed vertical air duct shall not exceed 2mm/m, and the total deviation shall not exceed 20mm.
暗裝風管位置應正確,無明顯偏差。
The position of the concealed air duct should be correct without any significant deviation.
風管安裝使用可調(diào)隔振支吊架時,應按設計的要求調(diào)整隔振支吊架的拉伸或壓縮量。
When using adjustable vibration isolation supports and hangers for air duct installation, the tension or compression of the vibration isolation supports and hangers should be adjusted according to the design requirements.
電加熱器前后800mm及防火閥兩側(cè)2000mm范圍內(nèi)的風管應采用不燃材料制作。
The air ducts within a range of 800mm before and after the electric heater and 2000mm on both sides of the fire damper should be made of non combustible materials.
非金屬及復合材料風管支管的重量不得由干管承受,風管所用的金屬附件和部件應做防腐處理。
The weight of non-metallic and composite material air duct branches shall not be borne by the main pipe, and the metal accessories and components used in the air duct shall be treated with anti-corrosion.
非金屬柔性風管應遠離熱源設備安裝。
Non metallic flexible air ducts should be installed away from heat source equipment.
安裝部位應無障礙物,操作場地應整潔,安全通道應完善、暢通,安裝用的腳手架及安全防護應無安全隱患。
The installation site should be unobstructed, the operating area should be clean, the safety passage should be complete and unobstructed, and the scaffolding and safety protection used for installation should have no safety hazards.
本文由 山東通風管道 友情奉獻.更多有關的知識請點擊 http://www.jnhxtcg.com/ 真誠的態(tài)度.為您提供為全面的服務.更多有關的知識我們將會陸續(xù)向大家奉獻.敬請期待.
This article is a friendly contribution from Shandong Ventilation Duct For more related knowledge, please click http://www.jnhxtcg.com/ Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Coming soon.
上一篇:山東通風管道:通風管道的安全措施本站圖片均由網(wǎng)站所有方提供,部分圖片來源于網(wǎng)絡,如有任何疑問請及時與我們聯(lián)系,未經(jīng)溝通本站不承擔相關法律責任!